Location and Limits of Affected Area:

Hill Street between South Forest Avenue and Church Street.

Description of Work:

Corby Energy Services will be closing Hill Street between South Forest Avenue and Church Street for the construction of an underground duct bank for DTE.

Temporary Traffic Control Plan:

From Monday, Aug. 5, 2019 9AM through Tuesday, Aug 13, 2019 5PM, eastbound Hill Street will be detoured to northbound East University Avenue, then eastbound Willard Street, then southbound South Forest Avenue back to Hill Street. Westbound Hill Street will be detoured to northbound South Forest Avenue, then westbound Willard Street, then southbound East University Avenue, back to Hill Street.

To maintain the safety of all, please reduce speeds and drive cautiously through the detour route. We thank you in advance for your patience.

More information can be found at www.a2gov.org/roads