The following update was emailed on Nov 4th, 2019 by Chris Wall, Project Manager for the City of Ann Arbor. For any questions or concerns with this project (or to be added to his email list of construction updates), he can be contacted at 734-794-6410 ext 43661 or by email at cwall@a2gov.org
The following work by the contractor is on-going this week:
- Road work on Hill Street between Brown Street and Fifth Avenue.
- Road work on Greene Street between Hoover Avenue and Hill Street.
- If weather permits, we are planning to finish paving Hill Street and Greene Street later this week.
All major water main and storm sewer work has been completed. There are a couple water services being worked on and each property impacted by this work are being consulted with directly.
The Hill Street (between Brown and Fifth), Greene Street (between Hill and Hoover), and Fifth Avenue (at Hill) closures remain in effect. The suggested detour route is Madison to Main, to Hoover, to Division.
Additional information about the Hoover, Greene, & Hill Improvement project is also available at a2gov.org/HooverGreeneHill
I previously posted about this project here:
https://www.a2elnel.com/post/hoover-greene-hill-project-update-oct-16th
https://www.a2elnel.com/post/hoover-greene-hill-project-update-sept-30th
https://www.a2elnel.com/post/hoover-greene-hill-project-update-sept-2nd
https://www.a2elnel.com/post/hoover-greene-hill-project-update-aug-26th
https://www.a2elnel.com/post/hoover-greene-hill-project-update-aug-12th
https://www.a2elnel.com/post/hoover-greene-hill-project-update-aug-5th
https://www.a2elnel.com/post/hoover-ave-traffic-control-plan-june-12th-to-july-26th
https://www.a2elnel.com/post/hoover-greene-hill-project-update-june-3rd
https://www.a2elnel.com/post/hoover-greene-hill-project-update-may-28th
https://www.a2elnel.com/post/traffic-control-plan-may-6th-30th-on-hoover-ave
https://www.a2elnel.com/post/hoover-greene-hill-construction-begins-may-6th