ITC State-Pioneer Transmission Line Project Update July 31st

Aug 1, 2019 | Construction

ITC Michigan, through its ITC Transmission subsidiary, is constructing approximately three miles of 120,000 volt (120kV) double-circuit transmission line to connect the State and Pioneer substations. This project supports electric reliability and increases capacity in the Ann Arbor area. Construction began in late 2018 and will take approximately eight months.

More information about the project can be found here:

https://www.itc-holdings.com/projects-and-initiatives/project-detail/2017/10/12/state-pioneer-transmission-line-project

ITC’s Customer Line and email for resident questions/concerns: 1.877.ITC.ITC9 (1.877.482.4829); general@itctransco.com

ITC State-Pioneer Transmission Line Project map May 2019

ITC has given me the following updates for July/Aug 2019:

Week of July 29:

No matting work

No foundation work

Wire pulling at several structures in areas listed below

  • north of Ann Arbor Public Schools building between Ann Arbor Railroad and S. State Street
  • north and south of Eisenhower Parkway
  • south of EB I-94

Lane closure on E. Eisenhower Pkwy and shoulder closure on I-94

Week of August 5:

No matting work

No foundation work

Wire pulling at several structures in areas listed below:

  • north of Ann Arbor Public Schools building between Ann Arbor Railroad and S. State Street
  • north and south of Eisenhower Parkway
  • south of EB I-94

Lane closure on E. Eisenhower Pkwy and shoulder closure on I-94

Week of August 12:

No matting work

No foundation work

Possible structure installations from north of E. Ellsworth Road to south of I-94


I previously posted about this project here:

https://www.a2elnel.com/post/itc-state-pioneer-transmission-line-project-update-june-27th

https://www.a2elnel.com/post/itc-state-pioneer-transmission-line-project-update-june-10th

https://www.a2elnel.com/post/itc-state-pioneer-transmission-line-project-update-may-2019