ITC Michigan, through its ITC Transmission subsidiary, is constructing approximately three miles of 120,000 volt (120kV) double-circuit transmission line to connect the State and Pioneer substations. This project supports electric reliability and increases capacity in the Ann Arbor area. Construction began in late 2018 and will take approximately eight months.
More information about the project can be found here:
https://www.itc-holdings.com/projects-and-initiatives/project-detail/2017/10/12/state-pioneer-transmission-line-project
ITC’s Customer Line and email for resident questions/concerns: 1.877.ITC.ITC9 (1.877.482.4829); general@itctransco.com

ITC has given me the following updates for Sept 2019:
Week of September 16:
- Remove matting work at structure north of North of Ann Arbor Public Schools building
- No foundation work
- No wire pulling work
Week of September 23:
- Miscellaneous clean-up, starting restoration work
- No foundation work
- No wire pulling work
Week of September 30:
- Miscellaneous clean-up, starting restoration work
- No foundation work
- No wire pulling work
I previously posted about this project here:
https://www.a2elnel.com/post/itc-state-pioneer-transmission-line-project-update-july-31st
https://www.a2elnel.com/post/itc-state-pioneer-transmission-line-project-update-june-27th
https://www.a2elnel.com/post/itc-state-pioneer-transmission-line-project-update-june-10th
https://www.a2elnel.com/post/itc-state-pioneer-transmission-line-project-update-may-2019