Maywood Ave Construction Update July 26th

Jul 27, 2019 | Construction

The following update was emailed on July 26, 2019 by Tesha Humphriss, Project Manager for the City of Ann Arbor. For any questions or concerns with this project (or to be added to her email list of construction updates), she can be contacted at 734-794-6410 ext. 43672, or at thumphriss@a2gov.org

Douglas N Higgins has finished all of the utility work associated with this project, including new water main, water service transfers, existing storm sewer repair, new storm sewer construction, and a handful of new storm sewer leads.  Currently, the contractor is bringing in stone and is rough grading the road base.

We are expecting to start pouring concrete curb and driveway approaches mid next week.  All affected property owners will receive a door knocker when access to your driveway will be restricted.

The contractor is starting to pencil in paving dates in early August; there is still some work to complete on the concrete restoration and road base before paving can occur, but I promise to share the paving dates with you once we firm them up.

I appreciate your patience during construction, please continue to reach out to me with any questions or concerns.


I previously posted about this project here:

https://www.a2elnel.com/post/maywood-ave-construction-update-july-12th

https://www.a2elnel.com/post/maywood-ave-construction-update-july-3rd

https://www.a2elnel.com/post/maywood-ave-construction-update-june-28th

https://www.a2elnel.com/post/maywood-ave-construction-update-june-21st

https://www.a2elnel.com/post/maywood-ave-construction-update-june-6th

https://www.a2elnel.com/post/maywood-ave-construction-update-may-31st

https://www.a2elnel.com/post/maywood-ave-storm-sewer-and-water-construction-scheduled-to-begin-may-28th

https://www.a2elnel.com/post/maywood-storm-sewer-and-water-main-upgrade-project-jun-aug-2019