Packard Rd closed at South Blvd (Aug 12th – 23rd)

Aug 15, 2020 | Construction

The following was issued by the City on Aug 7, 2020

This detour relates to water main construction on South Main Blvd I posted about previously:
https://www.a2elnel.com/post/south-blvd-water-main-construction-starts-july-27th

Notice of Temporary Traffic Control Plan:
Packard Road at South Boulevard
Wednesday, Aug. 12–Sunday, Aug. 23, 2020

Location and Limits of Affected Area:

Packard Road at South Boulevard.

Description of Work:

The contractor, ET Mackenzie Company, will install new water main at the intersection of Packard Road and South Boulevard; and repave the intersection.

For the safety of the traveling public and work crews, the following traffic control plan will be implemented.

Temporary Construction Traffic Control Plan:

Weather permitting, beginning Wednesday, Aug. 12–Sunday, Aug. 23, 2020, Packard Road will be closed at South Boulevard:

Southbound Packard traffic will be detoured west on Stadium Boulevard; south on South Industrial Highway; and east on Eisenhower Parkway to Packard Road.

Northbound Packard traffic will be detoured west on Eisenhower Parkway; north on South Industrial Highway; and east on Stadium Boulevard to Packard Road.

During construction, access for pedestrians will be maintained, with posted pedestrian detours as necessary. Emergency vehicle access to South Boulevard will be maintained from the south side of the intersection.

The city thanks all in advance for their patience.