Saxon, Waltham, Windsor Final Paving Rescheduled to Nov 5-7

Oct 29, 2020 | Construction

The following notice dated Oct 28, 2020 will be circulated by the City to property owners/residents in the affected area regarding the final operations of resurfacing project work planned for Saxon Street, Waltham Drive and Windsor Drive on Thursday, Nov 5 through Saturday, Nov 7, weather-permitting.

This work was originally scheduled for Oct 28-30:
https://www.a2elnel.com/post/saxon-waltham-windsor-final-paving-scheduled-oct-28-30

I previously posted about this resurfacing project here:
https://www.a2elnel.com/post/street-resurfacing-chaucer-mershon-saxon-waltham-windsor-winsted-worthington-yeoman


Due to weather conditions earlier this week and related scheduling conflicts the cold milling, pavement and base repair, and paving operations planned on Saxon Street, Waltham Drive and Windsor Drive have been delayed. We apologize for any inconvenience this may have caused.

Weather permitting; the City’s contractor, Cadillac Asphalt, now plans to perform this work on Thursday, November 5, 2020 through Saturday, November 7, 2020, between 7:00 a.m. and 8:00 p.m., as shown below.

  • Cold Milling (partial pavement removal): Thursday, November 5
  • Pavement and Base Repairs: Friday, November 6
  • Paving (top Course): Saturday, November 7

On these days, vehicular access to and from residences will be limited as intermittent closures and related delays will be present to accomplish these activities. Based on experience, the success of this work depends upon your assistance. Please kindly observe the following:

  1. Turn off all lawn sprinklers and keep the street free of all trash and recycle receptacles and/or bags, and compost carts.
  2. If you require use of your vehicle(s) during the times of the planned paving work, it is highly recommended you park legally on an adjacent street during working hours.
  3. If you have a special circumstance that may interfere with this work, please advise the contractor’s site supervisor, Jay Wartella (269-209-4588), either of the City’s project inspectors, Gary Shivley (734-765-8154) or Carl Emmons (517-605-9342), or the City’s project manager, David Dykman (734-794-6410 ext. 43685). We will do our best to accommodate you.
  4. As noted above, weather and related scheduling conflicts may delay this work. Please visit the following website to obtain schedule updates: https://www.a2gov.org/departments/engineering/Pages/Construction-Projects.aspx

Thank you in advance for your patience and cooperation during this improvement project.

The City of Ann Arbor/Public Services Area/Engineering & Cadillac Asphalt LLC